We’re pleased to share the March Blueprint Two progress report, with key updates related to the build and test, which remain our top priorities.

The team at Velonetic has made significant progress in building the new digital services, completing another five products since our last report, with a sixth scheduled for completion in March.
However, the remaining four products have presented additional challenges, and it’s now clear they will not be completed in Q1. Velonetic is now targeting the end of May for full core build completion.
The complexity and scale of this project and the commitment to deliver a functional product are driving the timeline as we head toward the finish line. The test strategy has been refined, and we will shortly be engaging with key programme stakeholders and associations to gather feedback on this document.
The goal is to move into User Acceptance Testing (UAT) in early Q2 2025. In collaboration with the LMA, IUA, and Lloyd’s, Velonetic has prepared an Exit Plan that outlines a controlled, evidence-based transition to DPS. We’re expecting the plan to be published by the end of March, with the aim of collecting all customer signatures by the end of June. Download the progress report here. We remain committed to keeping the market informed and engaged.
Yesterday we hosted the first virtual Blueprint Two session of 2025, with the recording and slides available on our Blueprint Two website. Our next in-person session will take place on Monday, 28 April, where we will share an update on our programme plan, with a significant focus on testing and cutover.
For the link to the progress report click here